Building Construction Information

 

 

 

  Q & A's About the Project 

 

Facility and Technology Study
Informational Letter

 

Floor Plans, Design, and Information

 

PROJECTED TIMELINE

v    March 10, 2008 – Sept. 2, 2008

– Site work on the athletic fields and front parking lots

v    March 10, 2008 – January 15, 2009

– New gymnasium construction

v    June 12, 2008 – August 29, 2008 

–  Remodel of classrooms in the 100-wing, band room, auditorium, courtyard and library

v    January 26, 2009- August 28, 2009

– Remodel of existing gym to function as cafeteria

v    June 11, 2009 to August 28, 2009

– Remodel of existing office area and cafeteria to function as new administrative offices