PROJECTED TIMELINE |
|
v
March 10, 2008 –
Sept. 2, 2008 |
– Site work on the athletic fields
and front parking lots |
|
v
March 10, 2008 –
January 15, 2009 |
– New gymnasium construction
|
|
v
June 12, 2008 –
August 29, 2008 |
– Remodel of classrooms in the
100-wing, band room, auditorium, courtyard and library |
|
v
January 26, 2009-
August 28, 2009 |
– Remodel of existing gym to
function as cafeteria |
|
v
June 11, 2009 to
August 28, 2009 |
– Remodel of existing office area
and cafeteria to function as new administrative offices |